stoop
MAP
LeaderboardAbout
Building SafetyHousing Conditions

1042 ATLANTIC AVENUE

Brooklyn · ZIP 11238 · BIN 3429784 · Crown Heights (North) · On record since Mar 21, 2024 · Built 2025

NeighborhoodⓘCrown Heights (North)
About average for Crown Heights (North)
More complaints than 59% of residential buildings in Crown Heights (North) over the last 10 years. Size-normalized by building volume.
59th pct
Activity TrendsLast 5 years
Complaints have increased in the last 2 years
↑ Up 267% in the last 2 years (33 vs 9 prior 2 yrs)
50250'24'26
Complaint SeverityⓘLast 10 years
About as many serious complaints as similar buildings
36 Priority A and B complaints over 2 years — 16.1 per year on average. Size-normalized by building volume.
16.1/yr68th pct(med. 0.1/yr)fewermedianmost
Department of Buildings Complaints
Total complaints since 2024
46
2 active
Total Priority Aⓘ
10
Total Priority Bⓘ
26
No Access for Inspection (past 5 yrs)ⓘ
0%
0 complaints
Complaints over time
5 yrsAll time

First filed Mar 21, 2024. Latest: Mar 18, 2026.

Top complaint types
5 yrsAll time
A — ImminentB — SeriousC — StandardD — Minor
Complaint log
46total
Active onlyAll
DateComplaint typePriorityStatusClosedOutcome
Mar 18, 2026

Elevator: Multiple Devices on Property

6M

CACTIVE—
See something wrong? File a complaint with 311
—
Feb 20, 2026

Elevator: Multiple Devices on Property

6M

CACTIVE——
Feb 8, 2026

Construction Safety Compliance (CSC) Action

8A

BCLOSEDFeb 17, 2026

Stop work order fully rescinded n

Jan 9, 2026

Elevator: Multiple Devices on Property

6M

CCLOSEDJan 22, 2026

No violation warranted for complaint at time of inspection

Dec 20, 2025

Construction Safety Compliance (CSC) Action

8A

BCLOSEDDec 20, 2025

Ecb violation served

Dec 20, 2025

Construction Safety Compliance (CSC) Action

8A

BCLOSEDDec 30, 2025

Stop work order fully rescinded n

Sep 8, 2025

Elevator: Multiple Devices on Property

6M

CCLOSEDJan 15, 2026

No violation warranted for complaint at time of inspection

Sep 4, 2025

Construction: Contrary/Beyond Approved Plans/Permits

83

BCLOSEDNov 6, 2025

Stop work order partially rescinded p

Sep 4, 2025

Construction: Contrary/Beyond Approved Plans/Permits

83

BCLOSEDSep 4, 2025

Building violation issued for failure to obey stop work order

Aug 11, 2025

Construction: Contrary/Beyond Approved Plans/Permits

83

BCLOSEDAug 11, 2025

Stop work order fully rescinded n

Aug 11, 2025

Construction: Contrary/Beyond Approved Plans/Permits

83

BCLOSEDNov 6, 2025

Stop work order partially rescinded p

Jul 24, 2025

Debris – Excessive

09

BCLOSEDSep 19, 2025

No violation warranted for complaint at time of inspection

Jul 15, 2025

Construction: Contrary/Beyond Approved Plans/Permits

83

BCLOSEDNov 6, 2025

Stop work order partially rescinded p

Jul 15, 2025

Construction: Contrary/Beyond Approved Plans/Permits

83

BCLOSEDNov 6, 2025

Stop work order partially rescinded p

Jul 12, 2025

Construction Safety Compliance (CSC) Action

8A

BCLOSEDJul 12, 2025

Ecb violation served

Jul 5, 2025

Construction Safety Compliance (CSC) Action

8A

BCLOSEDJul 5, 2025

Ecb violation served

May 31, 2025

Construction Safety Compliance (CSC) Action

8A

BCLOSEDMay 31, 2025

Ecb violation served

May 29, 2025

Debris/Building – Falling or In Danger of Falling

10

ACLOSEDJun 20, 2025

Stop work order fully rescinded n

May 24, 2025

Construction Safety Compliance (CSC) Action

8A

BCLOSEDMay 24, 2025

Ecb violation served

Jan 8, 2025

Work Contrary to Stop Work Order

86

ACLOSEDMar 11, 2025AF
Jan 8, 2025

Site Conditions Endangering Workers

91

ACLOSEDMar 11, 2025AF
Jan 5, 2025

Site Conditions Endangering Workers

91

ACLOSEDMar 11, 2025AF
Dec 25, 2024

Permit – None (Building/PA/Demo etc.)

05

BCLOSEDDec 26, 2024

Complaint unsubstantiated based on department records

Sep 18, 2024

Site Conditions Endangering Workers

91

ACLOSEDSep 25, 2024

Stop work order fully rescinded n

Sep 10, 2024

Construction: Contrary/Beyond Approved Plans/Permits

83

BCLOSEDSep 10, 2024

Stop work order fully rescinded n

Sep 9, 2024

Debris/Building – Falling or In Danger of Falling

10

ACLOSEDSep 23, 2024

Stop work order fully rescinded n

Sep 1, 2024

After Hours Work – Illegal

04

BCLOSEDSep 8, 2024

No violation warranted for complaint at time of inspection

Sep 1, 2024

After Hours Work – Illegal

04

BCLOSEDSep 21, 2024

No violation warranted for complaint at time of inspection

Aug 20, 2024

Construction: Contrary/Beyond Approved Plans/Permits

83

BCLOSEDAug 29, 2024

Stop work order fully rescinded n

Aug 2, 2024

Sustainability Enforcement Work Order

4S

BCLOSEDAug 12, 2024

No violation warranted for complaint at time of inspection

Jul 11, 2024

CSE: Tracking Compliance

7F

DCLOSEDSep 4, 2024AF
Jun 30, 2024

After Hours Work – Illegal

04

BCLOSEDJul 18, 2024

No violation warranted for complaint at time of inspection

Jun 18, 2024

Site Conditions Endangering Workers

91

ACLOSEDJun 20, 2024

No violation warranted for complaint at time of inspection

Jun 9, 2024

After Hours Work – Illegal

04

BCLOSEDJun 30, 2024

No violation warranted for complaint at time of inspection

Jun 3, 2024

CSE: Tracking Compliance

7F

DCLOSEDJun 3, 2024

No violation warranted for complaint at time of inspection

Jun 2, 2024

Site Conditions Endangering Workers

91

ACLOSEDJun 3, 2024

No violation warranted for complaint at time of inspection

May 25, 2024

Construction Safety Compliance (CSC) Action

8A

BCLOSEDMay 25, 2024

Ecb violation served

May 18, 2024

CSE: Tracking Compliance

7F

DCLOSEDMay 18, 2024

No violation warranted for complaint at time of inspection

May 10, 2024

After Hours Work – Illegal

04

BCLOSEDMay 19, 2024

No violation warranted for complaint at time of inspection

May 6, 2024

After Hours Work – Illegal

04

BCLOSEDMay 24, 2024

No violation warranted for complaint at time of inspection

Apr 19, 2024

After Hours Work – Illegal

04

BCLOSEDMay 20, 2024

No violation warranted for complaint at time of inspection

Apr 12, 2024

CSE: Sweep

7G

DCLOSEDApr 15, 2024

Ecb violation served

Apr 7, 2024

Failure to Maintain

73

CCLOSEDApr 8, 2024

Ecb violation served

Mar 24, 2024

CSE: Tracking Compliance

7F

DCLOSEDMar 25, 2024

Ecb violation served

Mar 21, 2024

Site Conditions Endangering Workers

91

ACLOSEDApr 5, 2024

Stop work order fully rescinded n

Mar 21, 2024

Site Conditions Endangering Workers

91

ACLOSEDApr 5, 2024

Stop work order fully rescinded n

CACTIVE
Mar 18, 2026
Elevator: Multiple Devices on Property
6M
CACTIVE
Feb 20, 2026
Elevator: Multiple Devices on Property
6M
BCLOSED
Feb 8, 2026
Construction Safety Compliance (CSC) Action
8A
Closed Feb 17, 2026

Stop work order fully rescinded n

CCLOSED
Jan 9, 2026
Elevator: Multiple Devices on Property
6M
Closed Jan 22, 2026

No violation warranted for complaint at time of inspection

BCLOSED
Dec 20, 2025
Construction Safety Compliance (CSC) Action
8A
Closed Dec 20, 2025

Ecb violation served

BCLOSED
Dec 20, 2025
Construction Safety Compliance (CSC) Action
8A
Closed Dec 30, 2025

Stop work order fully rescinded n

CCLOSED
Sep 8, 2025
Elevator: Multiple Devices on Property
6M
Closed Jan 15, 2026

No violation warranted for complaint at time of inspection

BCLOSED
Sep 4, 2025
Construction: Contrary/Beyond Approved Plans/Permits
83
Closed Nov 6, 2025

Stop work order partially rescinded p

BCLOSED
Sep 4, 2025
Construction: Contrary/Beyond Approved Plans/Permits
83
Closed Sep 4, 2025

Building violation issued for failure to obey stop work order

BCLOSED
Aug 11, 2025
Construction: Contrary/Beyond Approved Plans/Permits
83
Closed Aug 11, 2025

Stop work order fully rescinded n

BCLOSED
Aug 11, 2025
Construction: Contrary/Beyond Approved Plans/Permits
83
Closed Nov 6, 2025

Stop work order partially rescinded p

BCLOSED
Jul 24, 2025
Debris – Excessive
09
Closed Sep 19, 2025

No violation warranted for complaint at time of inspection

BCLOSED
Jul 15, 2025
Construction: Contrary/Beyond Approved Plans/Permits
83
Closed Nov 6, 2025

Stop work order partially rescinded p

BCLOSED
Jul 15, 2025
Construction: Contrary/Beyond Approved Plans/Permits
83
Closed Nov 6, 2025

Stop work order partially rescinded p

BCLOSED
Jul 12, 2025
Construction Safety Compliance (CSC) Action
8A
Closed Jul 12, 2025

Ecb violation served

BCLOSED
Jul 5, 2025
Construction Safety Compliance (CSC) Action
8A
Closed Jul 5, 2025

Ecb violation served

BCLOSED
May 31, 2025
Construction Safety Compliance (CSC) Action
8A
Closed May 31, 2025

Ecb violation served

ACLOSED
May 29, 2025
Debris/Building – Falling or In Danger of Falling
10
Closed Jun 20, 2025

Stop work order fully rescinded n

BCLOSED
May 24, 2025
Construction Safety Compliance (CSC) Action
8A
Closed May 24, 2025

Ecb violation served

ACLOSED
Jan 8, 2025
Work Contrary to Stop Work Order
86
Closed Mar 11, 2025
AF
ACLOSED
Jan 8, 2025
Site Conditions Endangering Workers
91
Closed Mar 11, 2025
AF
ACLOSED
Jan 5, 2025
Site Conditions Endangering Workers
91
Closed Mar 11, 2025
AF
BCLOSED
Dec 25, 2024
Permit – None (Building/PA/Demo etc.)
05
Closed Dec 26, 2024

Complaint unsubstantiated based on department records

ACLOSED
Sep 18, 2024
Site Conditions Endangering Workers
91
Closed Sep 25, 2024

Stop work order fully rescinded n

BCLOSED
Sep 10, 2024
Construction: Contrary/Beyond Approved Plans/Permits
83
Closed Sep 10, 2024

Stop work order fully rescinded n

ACLOSED
Sep 9, 2024
Debris/Building – Falling or In Danger of Falling
10
Closed Sep 23, 2024

Stop work order fully rescinded n

BCLOSED
Sep 1, 2024
After Hours Work – Illegal
04
Closed Sep 8, 2024

No violation warranted for complaint at time of inspection

BCLOSED
Sep 1, 2024
After Hours Work – Illegal
04
Closed Sep 21, 2024

No violation warranted for complaint at time of inspection

BCLOSED
Aug 20, 2024
Construction: Contrary/Beyond Approved Plans/Permits
83
Closed Aug 29, 2024

Stop work order fully rescinded n

BCLOSED
Aug 2, 2024
Sustainability Enforcement Work Order
4S
Closed Aug 12, 2024

No violation warranted for complaint at time of inspection

DCLOSED
Jul 11, 2024
CSE: Tracking Compliance
7F
Closed Sep 4, 2024
AF
BCLOSED
Jun 30, 2024
After Hours Work – Illegal
04
Closed Jul 18, 2024

No violation warranted for complaint at time of inspection

ACLOSED
Jun 18, 2024
Site Conditions Endangering Workers
91
Closed Jun 20, 2024

No violation warranted for complaint at time of inspection

BCLOSED
Jun 9, 2024
After Hours Work – Illegal
04
Closed Jun 30, 2024

No violation warranted for complaint at time of inspection

DCLOSED
Jun 3, 2024
CSE: Tracking Compliance
7F
Closed Jun 3, 2024

No violation warranted for complaint at time of inspection

ACLOSED
Jun 2, 2024
Site Conditions Endangering Workers
91
Closed Jun 3, 2024

No violation warranted for complaint at time of inspection

BCLOSED
May 25, 2024
Construction Safety Compliance (CSC) Action
8A
Closed May 25, 2024

Ecb violation served

DCLOSED
May 18, 2024
CSE: Tracking Compliance
7F
Closed May 18, 2024

No violation warranted for complaint at time of inspection

BCLOSED
May 10, 2024
After Hours Work – Illegal
04
Closed May 19, 2024

No violation warranted for complaint at time of inspection

BCLOSED
May 6, 2024
After Hours Work – Illegal
04
Closed May 24, 2024

No violation warranted for complaint at time of inspection

BCLOSED
Apr 19, 2024
After Hours Work – Illegal
04
Closed May 20, 2024

No violation warranted for complaint at time of inspection

DCLOSED
Apr 12, 2024
CSE: Sweep
7G
Closed Apr 15, 2024

Ecb violation served

CCLOSED
Apr 7, 2024
Failure to Maintain
73
Closed Apr 8, 2024

Ecb violation served

DCLOSED
Mar 24, 2024
CSE: Tracking Compliance
7F
Closed Mar 25, 2024

Ecb violation served

ACLOSED
Mar 21, 2024
Site Conditions Endangering Workers
91
Closed Apr 5, 2024

Stop work order fully rescinded n

ACLOSED
Mar 21, 2024
Site Conditions Endangering Workers
91
Closed Apr 5, 2024

Stop work order fully rescinded n